Additional information
Simultaneous realization of construction works of production halls on several construction plots on the territory of TSSE caused the project to be a considerable logistic challenge. When realizing roads and sewerage system on the whole investment area, we had to provide constant access to the grounds adjacent to the site. Due to heavy soil conditions on site, 20-45 thick cement-bound material was placed underneath the whole road structure
The project in figures
- roadway width 7 m;
- length of the roads 11 km;
- stormwater drainage system 7,2 km
- retention tanks 18 000 m3
- sidewalks made of concrete blocks 30,500 m2