c

Modernization of the E20 railway line

The project in figures

  • Earthworks (trenches -38 000m3, embankments -1 800m3)
  • demolition: tracks - 8,24 km, turnouts - 33 items, junctions - 4 items
  • construction of tracks - 8,24 km, turnouts - 26 items, construction of a new tunnel 175m long and 9m wide, construction of one control room, construction of the one road hostel
  •  Iinstallation of networks 14tkm (single and doublewired network)
  •  piles -154 items
  •  gates -47 items

Last updated: 8/16/2017

Search or filter all our projects

Result

loading